A compact, 20-bed facility in Jefferson, Iowa, replaces an outdated jail with clear sightlines, secure circulation and daylight-filled spaces built for the people who work and live inside.
The following article was provided by the ISG team
JEFFERSON, Iowa—For years, the Greene County Jail operated on borrowed time. The aging facility with no way to separately house female inmates or other special populations, and no access to the natural daylight that Iowa now requires in jail housing. Without major upgrades, the county risked losing its jail altogether, and county leaders were direct with residents about what that would mean: transporting and boarding inmates in other counties at significant cost.
After two referendums in two years, Greene County voters approved a $10 million bond for a new jail in November 2023, clearing the 60% majority required. Ground was broken in March 2025, and in late August 2026 the county moved inmates into its new facility.
Project Snapshot
Total area
12,812 square feet
Structure
Single story, with a taller, daylit indoor recreation space
Capacity
32 beds
Key Partners
- ISG: Architecture and engineering
- DCI Group: Construction manager at risk
Timeline
- Final voter approval November 2023
- Groundbreaking March 2025
- Inmates moved in August 2026
A Collaborative Vision Brought to Life
Greene County entrusted ISG with the design and brought on DCI Group as construction manager at risk. Sherrif Jack Williams and the ISG design team toured other jails and incorporated lessons learned from each facility into a layout tailored to a rural county with a small staff and a growing need for space.
Designed Around Visibility
At the heart of the new jail is a central control room positioned to enhance visibility and allow for ultimate sightlines. Raised slightly above the housing areas and wrapped in mirrored glass, the control station gives detention officers a 180-degree view into both cell blocks and their day rooms from a single seat.
Direct sightlines matter because cameras can only do so much. Audio and video monitoring documents activity throughout the facility, but privacy requirements limit where cameras can point, such as toward showers. A layout that lets staff observe housing areas directly reinforces a constant sense of supervision that protects inmates and officers.
The two housing units are designed as near mirror images of each other. That symmetry gives the sheriff’s office flexibility to assign populations as needs change and, for the first time, Greene County can separately house female inmates.

Secure Circulation
The design keeps the public, staff and detainees on strictly separate paths. Members of the public enter on the north side into a lobby and office area, and visitation happens remotely through a dedicated communication system rather than face to face. Attorneys meet with clients through secure glass.
Arrested individuals arrive through a vehicle sally port large enough for two patrol vehicles and two ambulances. Its doors are interlocked, so vehicle doors stay secure until both overhead doors are closed. From there, individuals move to one of two holding cells, each able to hold up to eight people, while booking is completed. A secure staff-only corridor wraps the housing units, allowing officers to conduct regular wellness checks and escort detainees without crossing public areas. Layered secure zones throughout the building give staff multiple fallback positions and buy time for backup to respond if a situation escalates.
Wellbeing
ISG’s design also addresses the mental toll of confinement. Unbreakable windows set high in the cell walls bring natural daylight into housing areas, helping detainees maintain a sense of time and a healthy circadian rhythm. An indoor recreation room, rising to about 25 feet with windows on all four sides, offers a bright, open space to walk or socialize, a meaningful break from the day room and cell.
“The goal of logistical operations at correctional facilities is to maintain order, safety, and facility security,” said ISG architect Jason Adams. “When a building’s layout works with daily operations instead of against them, it creates a safer environment for staff and the people in their care.”
Measurable Impact
The new jail is already making a difference.
Construction was completed ahead of schedule, with a final project cost of $10.3 million. Now open, the new Greene County Jail gives the county a modern, right-sized facility built to serve for decades. It shows that even a small rural community can deliver a jail that meets today’s standards for safety, dignity, and efficiency.